Benedum Hall Transformation
Transformation Timeline and Project Overview
Current renovations:
- The sub-basement, basement, and second floor have been vacated for construction. Those offices moved to other places in Benedum, Posvar, Cathedral of Learning, and the Center for Bioengineering.
- The Mascaro building is scheduled to be completed by mid-August 2009.
- The auditorium is scheduled to be completed by mid-July 2009. (Conversion of space into classrooms.)
- The construction of the Holzman Learning Center (10th floor) is complete. Classes have been held in the center since fall 2008.
Upcoming renovations:
- The new ground floor will be finished in November 2009 and will be converted into classrooms, a café, student organizations, and the library.
- The sub-basement has a newly added mezzanine level and will become a computing lab and the library stacks. This is scheduled to be completed mid-July 2009.
- Renovations of the first floor will begin in December 2009 through April 2010.
- Renovations of the fourth floor will begin January 2010 through late July 2010.
- Renovations of the fifth floor will begin in July 2010 through December 2010.
- Phase II (floors 6-12) will begin shortly after.
|